Mumbai’s Vile Parle Cypher is giving unheard rappers a voice Enrich and Ultimo impress Karnataka CM Signals Review of 5% Park Land Amendment Bill in Assembly When an organisation deviates from its values, faith of those associated with its ideology is shattered: Kaushal Kishore Andhra Pradesh CM Urges Farmers to Cede Land for Narsapuram Port Development Rajasthan local body polls: Congress launches ‘Gen Z for Change’ campaign At least 30 houses set ablaze in three Manipur villages; 1 injured: Police CBI Faces 7,229 Pending Corruption Cases, 409 Over 20 Years Old ‘Cauvery our legal right’: Tamil Nadu CM Vijay opens Mettur dam for Samba rice cultivation, drinking water needs MP woman, 21, murdered by father, uncle for working outside, short hair: Police Mumbai’s Vile Parle Cypher is giving unheard rappers a voice Enrich and Ultimo impress Karnataka CM Signals Review of 5% Park Land Amendment Bill in Assembly When an organisation deviates from its values, faith of those associated with its ideology is shattered: Kaushal Kishore Andhra Pradesh CM Urges Farmers to Cede Land for Narsapuram Port Development Rajasthan local body polls: Congress launches ‘Gen Z for Change’ campaign At least 30 houses set ablaze in three Manipur villages; 1 injured: Police CBI Faces 7,229 Pending Corruption Cases, 409 Over 20 Years Old ‘Cauvery our legal right’: Tamil Nadu CM Vijay opens Mettur dam for Samba rice cultivation, drinking water needs MP woman, 21, murdered by father, uncle for working outside, short hair: Police
LEADNEWS24

Dhaka Metro Rail Cost Surges to Over Tk 2 Trillion: Causes and Concerns

The projected cost for Dhaka's MRT Line-1 and Line-5 (Northern Route) has more than doubled to Tk 2.14 trillion due to design changes, inflation, and currency depreciation, awaiting Planning Commission approval.

P
Prothom Alo English
Aug 30, 2026 · 3 min read
Dhaka Metro Rail Cost Surges to Over Tk 2 Trillion: Causes and Concerns

The estimated cost of two major Dhaka metro rail projects has more than doubled, rising from an initial projection of Tk 938 billion to Tk 2.13985 trillion, according to revised proposals submitted by the Dhaka Mass Transit Company Limited (DMTCL) to the Planning Commission. The proposed increase is now under review by government authorities, with a technical committee’s report endorsing the higher costs as justified.

The two projects, MRT Line-1 and MRT Line-5 (Northern Route), are part of Bangladesh’s expanding urban transit network aimed at easing traffic congestion in the capital. MRT Line-1 will connect Kamalapur to Hazrat Shahjalal International Airport, combining elevated and underground sections, including a stretch from Nadda to Purbachal. MRT Line-5 (Northern Route) will run from Savar through Gabtoli, Mirpur, and Gulshan to Bhatara, also featuring mixed elevated and underground segments.

Officials at DMTCL, operating under the Road Transport and Bridges Ministry, cited multiple factors behind the cost surge: revisions to detailed designs, inflation, currency devaluation, delays, and technical modifications. The agency has already completed depot construction and is in the process of contractor appointments. The revised development project proposals were sent to the Planning Commission for approval after a technical committee, led by former BUET professor Shamim Z Bosunia, concluded that the cost escalation was unavoidable due to macroeconomic pressures and design expansions.

Financing for both projects comes from the Japan International Cooperation Agency (JICA), which has been engaged in multiple discussions with Bangladeshi authorities over cost adjustments. A seven-member technical committee reviewed the projects and affirmed that the cost increases—ranging from 130% to 160% over original estimates—were justified by global inflation, a 38% rise in the US dollar’s value against the taka, and expanded project scope. The Planning Commission is scheduled to evaluate the revised proposals today.

Transport Minister Sheikh Robiul Alam emphasized the necessity of metro rail for Dhaka’s survival, noting that postponement would only drive costs higher. Under revised estimates, MRT Line-1’s cost has jumped from Tk 525.61 billion to Tk 1.20 trillion, making it the second-most expensive infrastructure project in Bangladesh after the Rooppur Nuclear Power Plant, at Tk 38.66 billion per kilometre. MRT Line-5’s cost has risen from Tk 412.39 billion to Tk 931.91 billion, or about Tk 46.6 billion per kilometre.

Critics point to conditions set by JICA that limit competition in contractor selection. Professor Shamsul Hoque of BUET argued that costs would remain high unless the tender process allowed broader participation. He acknowledged that some cost increases were natural due to inflation and design changes but cautioned against “astronomical” figures driven by restricted competition.

The projects remain central to Dhaka’s urban mobility strategy, with Line-1 already under partial construction and both routes expected to reduce congestion and improve connectivity across the city.

#DhakaMetroRail #MRTLine1 #MRTLine5 #DMTCL #JICA #UrbanTransit #BangladeshInfrastructure #PlanningCommission

Source: Prothom Alo English. Rewritten by AI · How We Use AI →
View original source →

Comments (0)

Comments are moderated and may take a little while to appear.

No comments yet — be the first to weigh in.

Related
Enrich and Ultimo impress
South Asia

Enrich and Ultimo impress

Racehorses Enrich and Ultimo Impress in Tuesday Morning Workouts at Bengaluru Turf Club BENGALURU, Sept 1 – Two rising stars in India’s horse racing circuit, En...

2 weeks ago·3 min
Trending

We use cookies to improve your experience and analyze traffic.

Manage cookie preferences

Essential

Required for the site to function. Always active.

Analytics

Helps us understand how readers use the site.

Marketing

Used to personalize ads shown to you.